Ben Pond leads NUVO Construction. His background runs across industrial, commercial and large-scale construction. Here he answers what homeowners ask about renovating the basement in an older Edmonton home.
What Do You Find When You Open Up an Older Basement?
With an older home, it’s wise to expect a few things nobody could reasonably have known beforehand.
Take an early-1900s home in Westmount. The homeowners were already using the basement, but it was cold and limited. Once demolition started, we found only minimal insulation on the foundation walls. The rim joists had none. Rim joists are the wood framing that sits on top of the foundation wall.
We found hidden junction boxes, the boxes where wires join, and outdated electrical. There were also unsafe stairs, windows that didn’t meet code, failing teleposts and undersized pad footings. A telepost is an adjustable steel post that holds up the main beam. Pad footings are the concrete pads under each post. Foundation cracks, minor mold and asbestos turned up too. Cracked drywall upstairs had been showing the structural problems below.
Do You Test Older Homes for Asbestos?
Yes, any home built before 1990 gets third-party asbestos testing before we disturb anything.
If it comes back positive, a third-party abatement company removes it safely. Then a tester checks the air to make sure the abatement left nothing behind. A clearance letter confirms the space is safe. That letter is important. It means the home is safe for the family and for our team before any other work carries on.
Asbestos isn’t always where you’d expect it. On a 1960s home in Kenilworth, the test came back positive on the main floor. The abatement company removed it before demolition. Then we opened the basement ceilings and found asbestos in the tape on the old ductwork. The tape sat hidden above the ceiling, so there was no way to test it beforehand. That added about $4,000 for abatement, air testing and new duct boots from our HVAC trade. Duct boots are the fittings where the ducts meet the vents.
What If the Basement Floor Isn’t Level?
Sometimes you level it, and sometimes the slab has to come out. The slab is the concrete basement floor.
In Kenilworth, the floors needed about $2,600 more levelling than we planned to meet the flooring manufacturer’s spec.
Westmount was a different story. The slab was about 7 inches out of level from one end to the other. We talked it through with the homeowners and engineering. Then we chipped out the whole slab, dug down and poured a new one. We took out roughly 50,000 pounds of concrete and another 20,000 pounds of material by hand. A new floor height meant a whole new staircase too. The homeowners gained about 4 or 5 inches of headroom, which helps when finishing a basement with low ceilings.
Why Is My Old Basement So Cold?
Often the walls have little or no insulation, and the cold pulls down comfort upstairs too.
That was the case in Westmount. We used about four inches of spray foam, insulation sprayed on as a foam that seals gaps. It got the walls to about R-24, which beat the code minimum. R-value is how well insulation holds in heat, and higher is warmer. It made a significant difference in comfort.
What About the Old Plumbing in an Older Basement?
Not every older home has old plumbing, but it comes up more often, so we recommend planning for it.
Kenilworth still had its original copper drain stack. The stack is the main vertical drain pipe that carries waste out of the house. We broke the concrete and moved the stack into the new bathroom wall. A cleanout, the access cap for clearing the drain, sat too high, so we lowered it. Then we re-piped the stack up to the main floor while everything was open.
On a recent Westmount job, the water lines in the basement bathroom ran along the cold outside wall. They had been freezing. We moved them into a new plumbing wall where they’d stay warm. The shower and the water meter were moving too, so we broke out the bathroom floor and poured it again. That one was on the bigger side, but it’s not something we see often.
How Do You Plan for Surprises in an Older Home?
We talk these things through with our clients at the consultation, especially in older homes.
Because of our experience, we know what to look for. We’re making recommendations all the time based on what we can see and what we know about older homes. Surprises like these can add to the cost of a basement development in Edmonton. That’s why we recommend planning for them.
Every older home is different. In Westmount, we refinished old structural lumber that couldn’t carry load anymore into shelving and benches for the basement.
About the author
Ben Pond, CEO and Director, NUVO Construction
Ben leads NUVO. He guides the field team, sales and the direction of the company. His background runs across industrial, commercial and large-scale construction, from schools to refineries to major infrastructure.
Headshot: the photo on the live About page (wp-content/uploads/2026/07/DSCF1799.jpg). Alt text: Ben Pond, CEO of NUVO Construction.